Bay County International Airport Construction Update

By Guest | July 10, 2009

Construction Update: 7/2/2009
Posted: 09 Jul 2009 06:57 AM PDT

Contract 1: Heavy Civil and Airfield Lighting
In general, base bid earthwork and Main Access Road are significantly completed. All of the P-403 asphalt base and 99% of the 15? concrete paving lanes have been placed on 8,500 linear feet of Runway 16-34. On the taxiways and main apron, all lime rock base and the first 2? lift of P-401 base have been placed.

Approximately 89% of contract is complete with 71% of the contract time used. All interim milestones being met or exceeded.

Production volumes in place are as follows:

There is an average of 97 workers and 150 pieces of equipment on site daily.

Contract 2: Terminal Building, ATCT and Support Buildings
Review of architecturally related features continues. Site inspections by Bay County and internal threshold inspections actively continue and are being tracked in log format.

Approximately 35% of the contract is complete with 43% of the contract time used.

Terminal

Air Traffic Control Tower

Terminal Support Facilities

Rental Car Facility

An average of 115 personnel are on site daily.

Contract 3: Utility Contract
The contract has been executed and all necessary submittals, insurance and bonds have been received from the Contractor.

On January 13, 2009 a limited Notice To Proceed was issued for the onsite utilities only. The final notice to proceed for remaining offsite work was issued on January 20, 2009.

Approximately 40% of contract work is complete with 46% of the contract time used. All interim milestones are being met or exceeded.

Production volumes in place to date are as follows:

Main Access Road

Joyner Road

GA Access Road

Lift Station

Force Main on CR 388

Fuel Farm

Booster Station

An average of 32 workers and 22 pieces of equipment are on site daily.

Contract 4: Landscape/Hardscape Contract
The contract was executed on June 2, 2009 in the amount of $2,957,056.52. A partial Notice to Proceed was released on June 8, 2009 for the seeding and erosion control measurements only along the Main Access Road and LEED area with a not to exceed amount of $600,000.00.

Production volumes in place to date are as follows: